Project/Construction Update

Construction on the Phase 2 of 95 Express began in November 2011. Construction will last approximately three years and cost an estimated $106 million. 95 Express Phase 2 will extend the existing express lanes north from the Golden Glades Interchange, in Miami-Dade County, to Broward Boulevard, in Broward County, by converting the existing High Occupancy Vehicle (HOV) lanes to two express lanes in each direction. Other work includes: installing Intelligent Transportation System (ITS) components; modifying the Ives Dairy Road interchange; bridge widening at specific locations; and installing new noise walls at locations between Hollywood Boulevard and Taft Street.

UPDATE: June 2013

With the start of Hurricane Season on June 1, please be advised that the contractor has an approved Hurricane Preparedness Plan, which will be implemented in the event of severe weather.
 

I-95 Express Phase 2:

  • Phase 2 of construction continues with installation of tolling and ITS equipment in the median area along I-95 throughout the project limits. The contractor is performing this work behind barrier wall during daytime hours with no impacts to traffic. This phase is expected to be completed in spring 2014.
  • Bridge widening is underway at Hollywood Boulevard, Stirling Road in Broward County and over the Snake Creek Canal in Miami-Dade County. Nighttime lane closures on local streets take place Sunday night through Thursday night, from 9 p.m. to 5 a.m.  Entrance and exit ramps are closed as necessary, during nighttime hours. Bridge widening at Hallandale Beach Boulevard will begin in summer 2013.
  • Overhead sign installation will begin this month and will require nighttime lane closures as well as lane closures on adjacent entrance and exit ramps. The contractor will begin at the south end of the project, near the Golden Glades Interchange and work northward on the northbound side of I-95. This will take several months to complete.

The project is currently on schedule with anticipated completion in late 2014.

Ives Dairy Road:
This project is nearing completion as the contractor completes final "punch list" items on Ives Dairy Road.  No lane closures are anticipated for Ives Dairy Road. However, closures on the entrance and exit ramps will continue as needed in conjunction with work on I-95. 

For details about current traffic conditions please go to: www.fl511.com


95 Express

A program of the Florida Department of Transportation.